Keystone Pipeline
Facility Type: Pipeline
Scope: New Construction
Owner: TransCanada (developer and operator); ConocoPhillips
Location: Hardisty, Alberta to Cushing, Okla. and Patoka, Ill.  United States
Region: North America
Modified:  September 13, 2010
Images:


Project description

Keystone Pipeline, a partnership between TransCanada and ConocoPhillips, will measure 2,148 miles from Hardisty, Alberta to Cushing, Okla., and Patoka, Ill. The Canadian portion of the pipeline, from Hardisty to the Canada/U.S. Border, entails converting 537 miles of existing Canadian pipeline from natural gas to crude oil transmission service and constructing 232 miles of pipeline, pump stations, and terminal facilities at Hardisty, Alberta.

The U.S. portion of the project calls for constructing 1,379 miles of pipeline and several pump stations along the route.

The initial capacity of the pipeline will be 435,000 barrels per day and will increase to 590,000 barrels per day. Ultimately, TransCanada would like to increase the capacity to 1.1 million by 2012. Commercial operations for the first phase began in June 2010.

Keystone has contracts with shippers totaling 495,000 barrels per day with an average term of 18 years.

The new pipeline will be 30 inches (76 centimeters) in diameter from Alberta to Illinois. The diameter will increase to 36 inches (91 centimeters) from the Nebraska/Kansas border to Cushing, Okla. While the industry standard of buried pipeline is 24 inches, the Keystone Pipeline will be buried 48 inches underground.

The pipeline expansion and new construction is expected to cost $7 billion, but the total Keystone Project investment will be approximately $12.2 billion.

TransCanada is developing, constructing, and operating Keystone.

Bakken Marketlink Project

On Sept. 13, 2010, TransCanada launched a binding open season for Keystone and Keystone XL capacity geared toward producers in the growing Bakken Shale play in the Williston Basin. TransCanda has proposed allocating 100,000 b/d of contract capacity on Keystone from Baker, Montana, to Cushing, Okla., and on Keystone XL from to Port Arthur, Texas. In effect, Bakken producers would have a direct link to the Cushing, Okla., oil storage hub and to Gulf Coast refining facilities.

TransCanada proposes building piping, booster pumps, meter manifolds, and two terminals -- one at Baker and another at Cushing. Two of the three storage tanks at Baker would each be capable of storing 250,000 barrels of oil from third-party pipelines and terminals. The third, 100,000-barrel-capacity tank at Baker would be used for operational purposes. The two tanks at the Cushing terminal, each a capacity of 250,000 barrels, would be used for delivery batch accumulation and would link to third-party pipelines and tank farms.

The estimated cost of facilities proposed for the Bakken Marketlink Project is $140 million, and TransCanada anticipates the project to begin service in the first quarter of 2013. The open season period is set to expire on November 10, 2010.

  Key Stats
Project type:
new construction and expansion
Pipeline type:
crude oil
Diameter:
30-inch (76-centimeter) from Alberta to Illinois; 36-inch (91-centimeter) from the Nebraska/Kansas border to Cushing, Okla.
Capacity:
435,000 b/d in late 2009; to be expanded to nominal capacity of 590,000 b/d in late-2010, then increased to 1.1M b/d by 2012
Length:
2,148 miles (3,456 km)
Committed capacity:
Keystone has contracts with shippers totalling 495,000 b/d with an average term of 18 years.
Contractors:
Universal Ensco Inc. (survey and design engineering); Canadian Pipeline Construction: Ledcor Pipeline Limited, Pioneer Truck Lines Ltd. (pipe offloading and stockpiling); U.S. Pipeline Construction: Henkels & McCoy, Inc., Michels Corp., Mid West Constructors (consortium of HC Price, Gregory & Cook, and Sheehan), T.G. Mercer (pipe offloading and stockpiling)
Shippers:
Valero Energy Corp.
In service:
2009
Cost:
$7B
  Related Articles
Suncor CEO Assails U.S. Delays In Approving Keystone XL
Apr 29, 2014 - The chief executive of Canada's largest oil producer criticized U.S. government delays in approving new cross-border pipeline projects on Tuesday.
Canada Oil-by-rail Deliveries in 2013 Lagged U.S. Estimate
Mar 05, 2014 - Far less Canadian oil sands crude reached the Gulf Coast by rail last year than the U.S. State Department had been expecting, according to data that could flavor the final stages of the Keystone XL pipeline debate.
TransCanada CEO: 'Extremely Confident' to Receive Keystone XL Approval
Jun 03, 2013 - Russ Girling on Friday said he hopes that the U.S. State Department will complete its environmental review of Keystone XL by mid-summer.
House Passes Bill to Speed Keystone Approval
May 23, 2013 - The bill, which won votes from 19 Democrats, eliminates the need for a special permit from Obama and declares a 2011 environmental review of Keystone sufficient.
EPA Chief Gives a 'C' Grade to State Department Keystone XL Review
May 09, 2013 - The head of the EPA Wednesday gave the U.S. State Department's review of the proposed Keystone XL pipeline a 'C' grade, but said there is "ample time and ability" to upgrade the analysis.
Green Activists Unlike Facebook Founder Over Apparent KXL Support
May 03, 2013 - Mark Zuckerberg has made millions of friends, but the Facebook founder's first foray into the political policy arena is quickly earning him some enemies.
TransCanada Pushes Back Proposed Keystone XL In-Service Date
Apr 26, 2013 - TransCanada pushes back the in-service date for its proposed Keystone XL pipeline as it awaits US approval for the controversial project.
TransCanada Fires Back at EPA Over Keystone XL Pipeline
Apr 24, 2013 - TransCanada has played the sovereignty card, arguing the United States' top environmental regulator is interfering on Canadian turf.
Keystone Criticism Misplaced, CEO Insists
Apr 22, 2013 - Keystone XL is "just a pipeline" that will have little impact on the pace of development in the oil sands, says the head of TransCanada Corp.
North American Energy Security Trumps Environment - Poll
Apr 22, 2013 - A majority of Canadians and Americans back TransCanada Corp.'s Keystone XL pipeline and suggest securing a stable energy supply for North America should be a bigger priority than reducing carbon emissions, a poll released Monday said.
Canada's Finance Minister Talks Up KXL with New US Treasury Secy
Apr 19, 2013 - Jim Flaherty made a pitch on Thursday for TransCanada's proposed Keystone XL pipeline with a top Obama administration official, telling Treasury Secretary Jack Lew that the contentious project is vital to both countries' economies.
AOPL Urges State Dept. to Approve KXL
Apr 18, 2013 - AOPL at a public hearing in Grand Island, Neb., Thursday reiterated the inherent safety of pipelines and the numerous special safety requirements that will apply to the Keystone XL pipeline.
API: Time to Approve Keystone XL
Apr 18, 2013 - The Keystone XL pipeline is in America's national interest and would be safe, according to the State Department's latest review, API Senior Downstream Manager Cindy Schild told reporters Thursday morning.
AFPM Applauds House Keystone XL Vote
Apr 17, 2013 - AFPM's president applauded the bipartisan approval of H.R. 3, the Northern Route Approval Act.
API CEO Calls for Leadership on Keystone XL
Apr 17, 2013 - American Petroleum Institute President and CEO Jack Gerard met with lawmakers in Washington to remind them of the broad public support and long-term economic benefits of the Keystone XL pipeline project.
High Hurdles Face Alberta's Carbon Reduction Plan
Apr 05, 2013 - The proposed ratcheting up of Alberta's carbon levy stands to win few plaudits from oil-sands opponents who have targeted TransCanada Corp.'s Keystone XL pipeline.
AOPL Applauds Majority Senate Support for KXL
Mar 22, 2013 - The Association of Oil Pipe Lines (AOPL) applauds Friday's support by a majority of U.S. Senators for the Keystone XL pipeline project.
COMMENTARY: Obama Is Caught Between Unions, Greens on KXL
Feb 20, 2013 - A brief moment February 13 showed why President Obama can't win when it comes to the Keystone XL pipeline. In front of the White House, protesters led by actress Daryl Hannah and the head of the Sierra Club demanded that Obama kill the project.
TransCanada Official: Keystone Decision From State Dept. 2-3 Months Away
Feb 13, 2013 - A senior executive of TransCanada Corp. said Tuesday the company expects final State Department approval for the Keystone XL pipeline expansion in two to three months, following a final U.S. environmental assessment.
Researchers: KXL Groundwater Risks in Nebraska Are Manageable
Dec 10, 2012 - Potential groundwater contamination risks posed by the Keystone XL pipeline in Nebraska are minimal and manageable under a “risk-managed” route proposed by a University of Nebraska-Lincoln water scientist, claim two researchers.
TransCanada: Keystone Pipeline Down for Three Days
Oct 18, 2012 - TransCanada Corp. (TRP) said Thursday its Keystone pipeline bringing oil from Western Canada to the U.S. will be down for three days after an inspection found an anomaly with the pipeline Wednesday.
Canada Orders TransCanada To Fix Safety Lapses On Keystone Line
Aug 22, 2012 - TransCanada Corp. (TRP) must install missing safety features on its original Keystone oil pipeline's pumping stations in Canada, the country's federal energy regulator ruled.
Lobbyist for Keystone: 'They Want to Eliminate Fossil Fuel Use'
Aug 01, 2012 - A lobbyist for a Canadian company that wants to build a pipeline from Alberta to Nebraska - said American politics are standing in the way.
Keystone 'Whistleblower' Alleges Shoddy Materials Along Original Pipeline
Jan 05, 2012 - A former inspector for a company that did work on TransCanada's original Keystone pipeline is accusing the Calgary-based company of a cavalier disregard for the environment.
TransCanada: Keystone XL Route Through Nebraska Is Safest Choice
Sep 12, 2011 - The Keystone XL pipeline will be constructed and operated at a safety level beyond that of any existing crude oil pipeline in the United States according to the recently released Final Environmental Impact Statement.
Nebraska Governor Asks Feds To Deny Keystone Pipeline Expansion Permit
Aug 31, 2011 - In a letter to President Barack Obama and Secretary of State Hillary Clinton, Gov. Dave Heineman expressed concern that TransCanada's proposed Keystone XL pipeline could damage the state's Ogallala Aquifer.
Keystone Poses 'No Significant Impacts' to Most Resources Along Path - US
Aug 26, 2011 - The U.S. State Department has finally reached a decision on the oil pipeline that TransCanada wants to build from Canada to Texas.
US Keeps Commitment to Decide Keystone Pipeline Approval by Year-End
Jul 22, 2011 - U.S. officials will release an environmental review in August of TransCanada's proposed 1,700-mile oil pipeline, a State Department official told reporters Friday.
Cause of Keystone Spills Fixed, TransCanada Executives Say
Jun 16, 2011 - TransCanada Corp. executives said they have found and fixed the cause of a series of small oil spills in the company's Keystone pipeline system.
EPA Criticizes State Dept's Environmental Review of Keystone Pipeline
Jun 08, 2011 - EPA officials are criticizing the State Department for its draft analysis of an oil pipeline that TransCanada wants to build between Canada and the U.S. Gulf Coast.
TransCanada Restarts Keystone Pipeline
Jun 06, 2011 - TransCanada Corp. (TRP, TRP.T) successfully restarted its Keystone pipeline Sunday after U.S. government officials reversed a decision made on Friday to bar the company from reopening the line.
State Dept. Wants Another Keystone XL Review
Mar 16, 2011 - The U.S. State Department said Tuesday it will require an additional environmental review of TransCanada Corp.'s much-debated Keystone XL pipeline expansion.
TransCanada Agrees to Extra Safety Measures for Keystone XL
Mar 11, 2011 - TransCanada will voluntarily add extra safety features to a proposed oil sands pipeline expansion that is causing concern among environmentalists and U.S. officials, a company executive said.
Imperial CEO: Keystone XL Is Vital to US
Mar 10, 2011 - A pipeline project that's pending U.S. approval is necessary to ensure the reliability and security of oil supplies to the world's largest oil consumer, the head of Imperial Oil Ltd. (IMO) said.
TransCanada Begins Keystone Deliveries to Cushing
Feb 09, 2011 - TransCanada Corp. on Wednesday announced the second phase of the US$12 billion Keystone Pipeline system has begun commercial deliveries of crude oil to Cushing, Oklahoma.
US Delays on Oil Sands Pipeline May Complicate Ties with Canada
Feb 07, 2011 - The U.S. State Department will decide in the first quarter whether it will approve another TransCanada pipeline that will bring oil sands crude to the Gulf Coast.
API Urges State Dept. to Approve Keystone Project
Jan 28, 2011 - API on Thursday urged the U.S. State Department to approve the Keystone pipeline project as soon as possible.
TransCanada Faces Legal Challenge from Okla. Landowners
Jan 17, 2011 - TransCanada Corp. faces a legal challenge from a group of Oklahoma landowners to its planned expansion of its oil sands pipeline to the U.S. Gulf Coast.
Alberta Touts Economic Benefits in Promoting Oil Sands
Dec 02, 2010 - In the PR war over the reputation of Canada's oil-sands industry, Alberta's Energy Minister Ron Liepert thinks he's found a winning strategy: jobs.
Clinton's Remarks on Keystone Support Stir Debate
Oct 25, 2010 - Senators from both parties urged Secretary of State Hillary Rodham Clinton on Thursday to clarify remarks she made that signaled likely U.S. support for a $7 billion pipeline to carry Canadian oil to refineries along the U.S. Gulf Coast.
TransCanada Launches Open Season for Bakken Marketlink
Sep 13, 2010 - TransCanada on Monday launched a binding open season to obtain firm commitments from interested parties for the Bakken Marketlink Project, which would provide crude oil transportation service from Montana to Oklahoma and to the Gulf Coast.
TransCanada: Oil Sands Exports Will Go To Asia If Blocked In US
Jun 30, 2010 - TransCanada Corp. struck back at environmentalists and some lawmakers vying to stop its effort to expand shipments of crude from Canada's oil sands to the U.S.
Oil Flows Through Keystone
Jun 09, 2010 - Beneath the skin of Buchanan County, Mo., a new artery of energy now flows. The Keystone pipeline, fetching crude oil from the northern ranges of Alberta, Canada, and transporting it to an Illinois refinery, has fossil fuel in motion.
State Dept. to Host Keystone XL Meetings in Montana
May 12, 2010 - Montanans will get a chance next week to comment on the recently completed draft environmental impact statement for TransCanada's Keystone XL Pipeline project.
Kan. County, Pipeline At Impasse Over Crossing Fee Issue
Nov 25, 2009 - Clay County (Kan.) Commissioners reached an impasse with Keystone Pipeline after much discussion with a representative Monday afternoon.
Kan. County Officials May Seek Excise Tax On Keystone Capacity
Nov 05, 2009 - Officials from several Kansas counties informally agreed Wednesday that they'll challenge a multimillion-dollar tax exemption the legislature handed to a Canadian pipeline company and might seek a new excise tax on the proposed pipeline's capacity.
Tunnel Below Miss. River Among Keystone's Biggest Challenges
Aug 11, 2009 - It's the ultimate in drilling challenges -- a tunnel 50 feet under the Mississippi River bottom, traversing a distance of 3,705 feet.
Keystone Work Wrapping Up In Northern S.D.
Jul 16, 2009 - As work finishes up on a crude oil pipeline being constructed through Day and Marshall counties, more workers will be leaving Aberdeen and heading to the southern part of South Dakota.
Weather Softens Keystone Schedule
May 14, 2009 - Wet weather and soft roads have pushed back the date that construction will resume on a crude oil pipeline running through Marshall and Day counties in South Dakota.
EDITORIAL: Pipeline Developer's Approach Seems Kinder
Apr 30, 2009 - The company that wants to build an oil pipeline through western South Dakota seems to be taking a more public-friendly approach this time around.
'Big Dog' Keystone XL To Boost Montana County Coffers
Apr 20, 2009 - Everything about TransCanada's Keystone XL Pipeline can be described in superlatives. But words like "huge," "mammoth" or "gargantuan" seem paltry descriptions of a 1,980-mile-long, $7.2 billion project.
Pipeline Company Defends Indian Steel Imports
Apr 09, 2009 - A Canadian pipeline company says an idled Illinois steel mill couldn't have supplied the pipe needed for a new pipeline being built in the Midwest.
GE Oil & Gas Inspects Section of Keystone
Apr 06, 2009 - GE Oil & Gas' PII Pipeline Solutions group is completing its largest pipeline inspection project by helping TransCanada evaluate the condition of an 864-kilometer (537 mile) portion of a natural gas pipeline in Canada.
WorleyParsons Wins Contract for Keystone Expansion
Mar 06, 2009 - WorleyParsons Limited has been awarded the detailed engineering, commissioning and construction support for the facilities of the Keystone Pipeline System expansion for TransCanada Keystone Pipeline, LP.
TransCanada's Kvisle: Oil Sands Delays Won't Slow Keystone
Feb 04, 2009 - TransCanada Corp. (TRP) said Tuesday it expects its Keystone oil pipeline to come into service in 2012 as scheduled, quashing earlier signals it could slow the project on delays to oil sands projects.
ND Okays Funding for Pipeline Interconnect Study
Jan 22, 2009 - The North Dakota Industrial Commission on Wednesday awarded a $89,750 contract to two companies for a feasibility study on constructing a pipeline to connect with one of TransCanada's Keystone pipelines.
Oil Sands Project Delays Could Be Boon for US Refiners
Jan 08, 2009 - The wave of project delays in Alberta's massive oil sands could benefit U.S. refiners at the cost of the provincial government's ambitions.
Keystone: In for The Long Haul
Jul 21, 2008 - Against the backdrop of the scenic Pembina Hills in North Dakota, the Keystone Pipeline inches its way southward, construction advancing at a rate of a mile or two a day.
NEB Okays Keystone Cushing Expansion
Jul 17, 2008 - The National Energy Board (NEB) on Thursday approved the TransCanada Keystone Pipeline GP Ltd. (Keystone) Cushing application to expand the Canadian portion of the Keystone pipeline, approved by the NEB on Sept. 20, 2007.
Valero: Prospective Keystone Shipper
Jul 16, 2008 - Valero on Wednesday affirmed that it has agreed to participate as a prospective shipper, subject to regulatory approvals, on the 500,000 barrel per day expansion of the Keystone crude oil pipeline system from Western Canada to the U.S. Gulf Coast.
TransCanada, ConocoPhillips To Expand Keystone To Gulf Coast
Jul 16, 2008 - TransCanada Corp. has announced plans to expand the Keystone crude oil pipeline system and provide additional capacity of 500,000 barrels per day from Western Canada to the U.S. Gulf Coast in 2012.
S.D. Judge Rules In TransCanada's Favor
May 15, 2008 - It was necessary for TransCanada to use eminent domain to gain access to land it needs to build an oil pipeline, a judge ruled Wednesday.
TransCanada Raises $1.3B In Common Share Offering
May 13, 2008 - TransCanada Corp. on Tuesday announced that it completed its public offering of 30,200,000 Common Shares at a price of $36.50 per Common Share.
EDITORIAL: Keystone II: Second Chance
May 08, 2008 - A sequel is in the making. TransCanada Corp. officials are planning to bring another crude oil pipeline through South Dakota. Keystone II would bring oil from Alberta to the Gulf Coast.
N.D. Measure Targets Pipeline Projects
May 02, 2008 - In the wake of pending approval of the Keystone Pipeline project in eastern North Dakota, two state residents want voters to stop similar projects in the future.
NEB Announces Location for Keystone Cushing Expansion Hearing
Apr 04, 2008 - The National Energy Board (NEB) announced that the April 8 hearing for TransCanada's Keystone Pipeline GP Ltd. Cushing Expansion application will be held at the Canadian Legion located at 207 - 5 Avenue East in Oyen, Alberta.
Pipes for Keystone Arrive In N.D.
Mar 31, 2008 - Twenty rail cars stacked with 30-inch pipe rolled into Milton, N.D., this weekend.
State Dept. Grants Keystone Permit; Work To Start In Q2
Mar 17, 2008 - The U.S. Department of State has issued a Presidential Permit to Keystone Pipeline authorizing the construction, maintenance and operation of facilities at the U.S. and Canada border to transport crude oil between the two countries.
State Dept Set To Issue Permit for Keystone
Mar 04, 2008 - The U.S. State Department intends to issue a permit this month for a $5.2 billion pipeline that would transport crude oil from Canada through seven states.
GE to Perform In-line Inspection for Keystone Project
Feb 19, 2008 - GE Oil & Gas has been awarded a contract by a subsidiary of TransCanada Corp. to deploy its "smart pig" to evaluate portions of TransCanada's 864-kilometer (537-mile) pipeline that runs through Saskatchewan and ends outside Winnipeg, Manitoba.
Canada Pipelines Vie for US Gulf Prize
Feb 04, 2008 - The race to connect Alberta's increasingly prolific oil sands producers with the U.S. Gulf Coast is entering its final stretch, with one pipeline proposal expected to break ahead of the pack in the coming months.
NEB Plans April 8 Hearing on Keystone Expansion
Feb 04, 2008 - The NEB has scheduled an oral hearing on an application from TransCanada Keystone Pipeline GP Ltd. for new pump stations, increased pumping capacity and pump station location changes on the proposed Cushing Expansion of the Keystone pipeline.
Keystone to Link Wood River to Oil Sands
Jan 25, 2008 - ConocoPhillips' acquisition of a 50-percent stake in the Keystone pipeline is the latest signal of the importance of Canadian oil to the company.
ConocoPhillips Acquires 50% Stake in Keystone
Jan 22, 2008 - ConocoPhillips and TransCanada Corp. on Tuesday announced that ConocoPhillips acquired a 50 percent ownership interest in the Keystone Oil Pipeline.
TransCanada Receives Final Keystone EIS from State Dept.
Jan 11, 2008 - TransCanada Keystone Pipeline, LP (Keystone) received the Final Environmental Impact Statement from the United States Department of State regarding the Keystone Pipeline project and Cushing extension.
N.D. Counties Stand to Reap Bounty from Keystone
Dec 28, 2007 - As 590,000 barrels of crude oil flow daily through a proposed pipeline, seven N.D. counties along the route will each get an estimated $1 million in annual tax revenue.
Siemens Wins $200M-plus Keystone Contract
Dec 19, 2007 - Siemens has been awarded a more than US$200 million (150 million Euro) contract from TransCanada Corp., to supply the Keystone Pipeline project (Keystone) with electrical equipment, electrical power supply and pumping equipment.
S.D. Lawsuits Question TransCanada's Eminent Domain Right for Keystone
Nov 05, 2007 - Two South Dakota court hearings are scheduled related to Trans-Canada's plans to create the 1,830-mile underground crude-oil Keystone pipeline.
CEP Appeals Energy Board's Keystone Decision
Oct 31, 2007 - For the first time ever, the Federal Cabinet has received a legal appeal to review the National Energy Board's decision and must now revisit the NEB's approval of the construction of the Keystone Pipeline in Alberta.
TransCanada: Keystone Construction to Begin in Spring
Oct 30, 2007 - TransCanada Corp. on Tuesday announced that it continues to make significant progress on the Keystone Pipeline project.
Canadian Union Appeals NEB's Keystone Decision
Oct 24, 2007 - The Communications, Energy and Paperworkers Union of Canada (CEP) on Wednesday launched an appeal to the Federal Cabinet of the National Energy Board's decision to allow construction of the Keystone Pipeline in Alberta.
South Dakota Sits at Crude Oil Crossroads
Oct 23, 2007 - South Dakota -- a major ethanol producer that typically sits on the alternative side of the fuel industry -- finds itself at the crossroads of two major oil projects.
S.D. Landowners Challenge TransCanada's Right to Eminent Domain
Oct 08, 2007 - With South Dakota's Public Utilities Commission looking on, the courtroom might be the next stop for TransCanada and some owners of land the company wants to use as it builds a crude oil pipeline.
NEB Approves Alberta-Manitoba Keystone Project
Sep 21, 2007 - The National Energy Board has approved the TransCanada Keystone Pipeline GP Ltd. application to construct and operate the Canadian portion of the Keystone pipeline project which would transport 435,000 barrels per day of crude oil.
TransCanada: Keystone Construction to Start Early Next Year
Sep 21, 2007 - TransCanada Corp. on Friday announced the National Energy Board (NEB) has approved an application by TransCanada Keystone Pipeline GP Ltd. (Keystone) to construct and operate the Canadian portion of the Keystone Pipeline project.
Feds Seek Input on Keystone EIS
Aug 10, 2007 - The public is invited to comment on the environmental impact statement for the proposed TransCanada-Keystone Oil Pipeline that would run through ten South Dakota counties.
S.D. Sets Dec. Hearing for Keystone
Aug 08, 2007 - A state hearing on a proposed pipeline that would pump crude oil through eastern South Dakota will be held in the first two weeks of December.
EDITORIAL: N.D. Should React, Not Overreact, to Pipeline
Jul 26, 2007 - The risk of a leak does not justify barring a vital pipeline from crossing N.D.
TransCanada's Keystone Oil Pipeline Adds Contracts
Jul 05, 2007 - TransCanada Corp. said that the proposed Keystone Oil Pipeline project has secured 155,000 barrels per day of additional firm contracts from Hardisty, Alberta to Cushing, Oklahoma with duration averaging 16 years.
TransCanada Wins NEB Approval to Transfer Facilities to Keystone
Feb 12, 2007 - The National Energy Board (NEB) has approved the transfer at net book value of a portion of TransCanada PipeLines Limited's Canadian Mainline natural gas transmission facilities to TransCanada Keystone Pipeline GP Ltd.
TransCanada Markets Keystone Pipeline Expansion, Cushing Extension
Jan 31, 2007 - TransCanada Corporation on Tuesday announced a binding Open Season for an expansion and extension of the proposed Keystone Oil Pipeline.
TransCanada Files Regulatory Application for Keystone Oil Pipeline Project
Jun 06, 2006 - TransCanada has filed an application with NEB to transfer a portion TransCanada's Canadian Mainline natural gas transmission facilities to the Keystone Oil Pipeline project to transport crude oil from Alberta to refining centers in the US Midwest.