Please enable Javascript to view this content.

According to information released by the U.S. Department of Energy (DOE) Friday morning, Sabine Pipe Line has restored partial compression at the Henry Hub complex near Erath, LA.

Like many oil and gas facilities in South Louisiana and South Texas, the Henry Hub was impacted by hurricanes Gustav and Ike. The Henry Hub is the pipeline system delivery point upon which the NYMEX natural gas futures contract is based. DOE also stated that force majeure has been lifted for some additional points along the Sabine Pipe Line system.

Further east on the Gulf Coast, BP Destin Pipeline has lifted the force majeure on the Pascagoula processing plant force majeure that it had declared on September 15. Projected volumes available on Destin's pipeline system were sufficient for the plant to resume normal operations, the company reported in a statement Thursday.

Based on the DOE report, which was current as of 8 a.m. Central time on Friday, Sept 19th, 27 natural gas pipelines were in the paths of Gustav and Ike. The table below highlights the status of each pipeline.

Status of Major Gulf Coast Natural Gas Pipelines
Pipeline As Of Status
Discovery Gas TransmissionSept. 17, 2008Offshore receipts remain unavailable pending assessments; some onshore receipt & delivery points accepting gas flow at reduced levels.
Enbridge (UTOS)Sept. 18, 2008All UTOS facilities remain under force majeure and are currently down and all points are shut-in. Damage assessments are still underway.
Garden Banks Gas PipelineSept. 17, 2008Crews on site continuing damage assessment -- minor damage visible. There is power generation but communication equipment is not functioning.
High Island Offshore SystemSept. 18, 2008Force majeure from Sept. 10 remains in effect. HIOS is currently securing equipment to locate a potential leak on its 42-inch line north of HIA-264. The equipment is expected to be on location in three days.
Kinder Morgan (Texas & Tejas)Sept. 17, 2008Force majeures remain in effect from Sept. 12. All firm storage customers can resume injections at 50% of their firm injection rights until further notice.
Manta Ray Offshore GatheringSept. 18, 2008Assessments continue on offshore platforms and facilities and repairs have started. A crew will be sent to assess and close valve on subsea assembly of the Boxer lateral tie-in at EW947 platform. Partial service expected by Friday, Sept. 26.
Mississippi Canyon PipelineSept. 17, 2008West Delta 143 platform is unavailable for gas flow. Venice plant has experienced water damage and will not be accepting gas. Alternate means to bypass plant to other processing plants and/or pipeline interconnects is being analyzed. Expected to be back in service by Sept. 21.
Natural Gas Pipeline Co. of AmericaSept. 18, 2008Notified customers that some delivery points along the Louisiana line are available to flow gas.
Nautilus Pipeline Co.Sept. 18, 2008Assessments continue and reports of the Burns Point location on system are intact with minor repairs needed. Downstream processing is ready once gas flow commences.
Sabine Pipe Line (Henry Hub)Sept. 18, 2008Force majeure has been lifted for some additional points along the system. Parital compression has been restored at the Henry Hub complex and the pipeline is closely monitoring its system.
Sea Robin Pipeline Co.Sept. 17, 2008Reduced flow due to damage, lack of processing, and continued shut-in as inspections continue. Some offshore systems have experienced some damage that will limit a full return to service. Processing is unavailable but gas flow can commence if at higher heating value.
Southern Natural Gas Co.Sept. 18, 2008Force majeure declared Sept. 17. Damage at interconnect with Sabine (Henry Hub) resulting in reduced gas flow. Repairs expected to be completed in 3-5 days. Supply impact from storms has decreased to approximately 340 MMcf/d.
Stingray Pipeline Co.Sept. 18, 2008Some onshore facilities (office building) sustained water damage; offshore facilities have minor damage and crews are working to repair visual damage and will perform further inspections in the coming days. Crews are being flown into onshore facilities due to the hazardous road conditions. System repairs could take up to 2 weeks.
Tennessee Gas PipelineSept. 17, 2008Tennessee has confirmed leaks on its 36-inch and 26-inch mainlines on the East Leg of the Blue Water system, in Ship Shoal 156/157.
Texas Eastern TransmissionSept. 17, 2008Texas Eastern estimates that producers have shut in 400,000 to 500,000 Dth/d of supply on its system due to Ike.
Texas Gas TransmissionSept. 17, 2008All systems on the pipeline are operational, but they are closely monitoring receipt points.
Transcontinental Gas Pipe LineSept. 17, 2008Emergency gas supply procedures remain in effect for only receipts on Southwest, Central, and Southeast Louisiana laterals of the system. Central Texas gathering system was accepting gas flow on Sept. 17.
Trunkline Gas PipelineSept. 17, 2008Houston office has reopened. Force majeure declared on Sept. 15. Some offshore systems have experienced some damage that will limit a full return to service. Flooding at Centerville Compressor Station is limiting gas flow to Henry Hub.
Venice Gathering SystemSept. 18, 2008Remains shut in from the effects of Gustav. Processing plant will not be available until first week in October--gas flow will remain at zero until plant is fully operational.
Dauphin Island GatheringSept. 16, 2008Force majeure lifted as Mobile Bay (Duke) processing plant completed maintenance. System will resume normal operations.
Black Marlin PipelineSept. 15, 2008Force majeure declared Sept. 12. No gas flow being accepted.
Gulf South PipelineSept. 18, 2008Critical period has been lifted as of gas day Sept. 18.
Northern NaturalSept. 16, 2008Scheduled gas flow through portions of the Matagorda Offshore Pipeline System.

Information provided by U.S. Department of Energy, Office of Electricity Delivery & Energy Reliability